26 Aug 2016, 00:00
Edgar Meza

PV auctions: More competition, but critics warn of target shortfalls

Photo: 漏 BSW Solar / Upmann
In August, Germany held the fifth tender in its new auction pilot scheme for payments to large-scale solar projects. While officials overseeing the programme continue to praise its results and declining price levels, critics warn that not enough solar capacity is being allocated and that Germany is falling behind its annual solar targets.

Mandated by its 2014 Renewable Energy Act (EEG), Germany shifted from a system of guaranteed feed-in tariffs (FiT) for solar projects to (pilot) auctions last year. In place of the fixed payments, the country introduced pilot tenders for large-scale, ground-mounted facilities. The move is envisaged to make Germany鈥檚 renewable energy subsidy programme more market-oriented and the sale of solar electricity more competitive, bringing it in line with EU strategy.

In the pilot, the auctions kicked off with 500 megawatts (MW) awarded in 2015, 400 MW in 2016 and 300 MW planned for 2017. The new EEG 2017 then calls for 600 MW of solar capacity to be auctioned annually while aiming for an overall annual capacity target of 2.5 gigawatts (GW), with smaller PV installations that do not participate in the tenders accounting for the rest. This means the lion鈥檚 share of new solar PV additions is still planned to come from such smaller installations, typically on homeowners鈥 rooftops which will continue to receive feed-in tariffs. The size of large-scale arrays is limited to 10 MW. So far solar PV is the only renewable energy source for which the auction system has been tested.

While some see the switch to auctions as a sensible move, particularly in view of the country鈥檚 grid limitations, others criticise what they deem to be a curbing of renewables, greater government control over the expansion of clean energy sources and increased limitations, like the 10 MW size restrictions.

Jenny Chase, manager of Solar Insight at Bloomberg New Energy Finance (BNEF), says the auctions are working 鈥渇airly well as a price discovery mechanism to find out what developers need to be paid to build.鈥 They are also working much better than FiTs at containing total build, she adds.

Auctions are oversubscribed

German Solar Association (BSW) spokesman David Wedepohl says the auctions have attracted high interest but adds that it鈥檚 too early to predict whether the annual tendered volume will be met. 鈥淭he industry is naturally hoping that the tendered volume of 600 MW a year will at least be close to realised in spite of all of the unnecessary restrictions and additional risks."

For developers, the auctions include new restrictions on system size, a limited amount of annual capacity that is being tendered and tougher conditions for smaller players. "The oversubscription of the pilot tender illustrates at least that there is still very large interest in solar technology. It鈥檚 still too early for a reliable forecast, however,鈥 Wedephol adds.

Like previous tenders, the August auction was significantly oversubscribed. The Federal Network Agency (BNetzA), which oversees the programme, initially tendered 125 MW and received 62 bids for a total volume of 311 MW. In the end, 130 MW went to 25 projects with an average bid price of 7.23 cents, down from the 7.41-cent average of the previous auction in April.

"The price level in the fifth round of tenders dropped slightly again despite a smaller number of bids," Federal Network Agency President Jochen Homann. The lower price shows that the auction has resulted in effective competition in the ground-mounted PV sector, Homann added.

The previous auction attracted 21 winning bids for 128.21 MW, with prices ranging from 6.94 to 7.68 cents per kilowatt-hour and well under the targeted 8-cent mark, the unit price achieved in the country鈥檚 third tender in December, which saw 204 MW spread across 43 projects.

Rainer Baake, state secretary at the economics and energy ministry, the process demonstrated that auctions work, adding that the strong and wide-ranging participation showed that solar developers had accepted the new system and that there were no obstacles to its further rollout.

Solar targets and construction lagging behind

German Solar Association (BSW) CEO Carsten K枚rnig at the time of the first auction that the high number of bidders reflected a significant readiness to invest in Germany鈥檚 PV sector, and that the low price level solar had reached also backed this up. K枚rnig expressed disappointment, however, that the government was not auctioning off much more solar capacity, particularly in view of the 170 bids, amounting to 700 MW. The 150 MW awarded accounted for about 20 percent of the overall capacity bid on. 鈥淭he apparent losers in the process are the more than 80 percent of remaining bidders who were also willing to build solar parks at very minimal cost,鈥 K枚rnig said, adding that the solar park tender volume of only 1.2 GW over three years fell well short of what was necessary to meet the country鈥檚 energy transition targets.

鈥淲ithout incurring any noticeable added costs, it would be possible to increase solar capacity many times over, an increase that is crucial in the effort to achieve effective climate protection,鈥 he said.

The BSW has continued to express disappointment at what it sees as too little solar capacity being tendered. Describing the results of this year鈥檚April auction as K枚rnig noted that PV prices had reached the level of onshore wind power. 鈥淭his shows that the energy transition can be achieved inexpensively with a significant expansion of photovoltaic hand in hand with wind power.鈥 Instead, PV expansion this year would clearly miss its annual target for the third time, he warned. 鈥淭his is completely at odds with the federal government鈥檚 climate and energy policy objectives.鈥

Indeed, the expansion of Germany鈥檚 solar capacity has lagged far behind the government鈥檚 annual 2.5 GW solar target. In the first six months of 2016, the country installed just .

In addition, despite the seeming success of the auction programme, actual construction of tendered projects has been slow. So far, just 25 percent of the winning projects in the first auction have been realised, . Of the projects selected in the second tender, only 27 percent had been installed through the end of July. Developers have two years to realise their projects. Many projects could go into operation towards the end of that period, Baake said.

Energy cooperatives on unequal playing field

While widely praised, the PV tender process has made it more difficult for smaller energy cooperatives and community solar initiatives, while favouring deep-pocketed investors and developers who can afford to offer lower rates.

鈥淒iversity and proximity is of course very important for the acceptance of the energy transition,鈥 says BSW鈥檚 Wedepohl. 鈥淧layers without portfolio advantages will have a very hard time in the long run and will likely only be able to build small ground-mounted systems of less than 750 kW using the conventional feed-in tariff programme.鈥 Wedepohl points out that energy cooperatives and power consumer projects were not very successful in the auctions. 鈥淭he results of the auction speak for themselves.鈥

BNEF鈥檚 Chase points out, however, that the auction鈥檚 focus on price excludes any developers that cannot be cost competitive as well as more complicated schemes, which take money to set up. 鈥淭hat is kind of the point.鈥 She adds that projects owned by power consumers 鈥渨on't bother with the auction system because they should be negotiating a power purchase agreement at prices competing with the much higher retail rates.鈥

According to Lekha Sidhar, a researcher at the Berlin-based Independent Institute for Environmental Issues (UfU), cooperatives are heavily dependent on a favourable policy climate. In her , Sidhar writes that in 2014, the number of new cooperatives fell sharply due to the changes in the EEG that reduced incentives and increased financial regulations. The PV auction system that partly replaced feed-in tariffs 鈥渉as put cooperatives on an unequal playing field,鈥 Sidhar writes. 鈥淐ooperatives and other small enterprises find it extremely difficult to compete with the tariffs offered by strategic investors.鈥

In addition, increased demand for investor protection has led to greater financial burdens for cooperatives. 鈥淪ince 2014, banks also require greater equity capital share from cooperatives before extending credit,鈥 Sidhar adds.

Nevertheless, the researcher points out that many cooperatives in Germany are weathering the storm through mergers, increased cooperation that is providing them with greater political strength and by moving into new areas, such as consulting services.

All texts created by the 威力彩玩法 are available under a . They can be copied, shared and made publicly accessible by users so long as they give appropriate credit, provide a link to the license, and indicate if changes were made.
« previous news next news »

Ask 威力彩玩法

Researching a story? Drop 威力彩玩法 a line or give us a call for background material and contacts.

Get support

+49 30 62858 497

Journalism for the energy transition

Get our Newsletter
Join our Network
Find an interviewee