威力彩玩法

News Digest Item
09 Jan 2018

Fitting more power into the existing grid

Agora Energiewende

A range of comparatively simple measures could increase the capacity of the German power grid within the next two to four years, energy think tank Agora Energiewende* finds in a study. An ad-hoc investment programme could improve the transmission grid to the degree that less re-dispatch measures are necessary. The improvements would cover the time before the new 鈥減ower transmission highways鈥 SuedLink and SuedOstLink are completed in the mid 2020s. Agora Energiewende suggest measures such as a better monitoring of overhead lines as their transmission capacity depended on surrounding weather conditions. Standard assumptions about temperature and wind speeds currently fail to fully exploit the transmission lines鈥 potential, the study says.

Read the study in German .

See the 威力彩玩法 dossier The energy transition and Germany鈥檚 power grid for more information.

*Like the 威力彩玩法, Agora Energiewende is a project funded by Stiftung Mercator and the European Climate Foundation.

All texts created by the 威力彩玩法 are available under a . They can be copied, shared and made publicly accessible by users so long as they give appropriate credit, provide a link to the license, and indicate if changes were made.

Journalism for the energy transition

Get our Newsletter
Join our Network
Find an interviewee