Fitting more power into the existing grid
A range of comparatively simple measures could increase the capacity of the German power grid within the next two to four years, energy think tank Agora Energiewende* finds in a study. An ad-hoc investment programme could improve the transmission grid to the degree that less re-dispatch measures are necessary. The improvements would cover the time before the new 鈥減ower transmission highways鈥 SuedLink and SuedOstLink are completed in the mid 2020s. Agora Energiewende suggest measures such as a better monitoring of overhead lines as their transmission capacity depended on surrounding weather conditions. Standard assumptions about temperature and wind speeds currently fail to fully exploit the transmission lines鈥 potential, the study says.
Read the study in German .